PU dewatering screen is commonly used dehydration equipment. Its main function is dehydration, desliming and deintermediation, and it is widely used in sand and gravel plants and coal preparation plants. When the dewatering screen is working, a proper angle is conducive to improving the dehydration effect and production efficiency of the dewatering screen. So what is the installation angle of the dehydration screen? What is the installation method? In response to these problems, the editor of Xinruituo will bring you relevant introductions.

Installation angle of PU dewatering screen
1. Generally speaking, there are no strict requirements for the installation of the dewatering screen, just keep it level. If the material is easy to be screened out, for example, the mesh is relatively large, and the feeding speed or amount of material is not very large, as long as the material passes through the top, it can be screened out. At this time, if you want to increase the time of the screening machine To increase the production capacity, you can tilt the outlet slightly downward.
2. If the material to be sieved is relatively small, the mesh is small, and the output requirement is not particularly high, we can also slightly increase the discharge port under the premise of ensuring the production time, which can improve our screening rate.
3. If the customer has no special requirements, usually the manufacturer will produce according to the standard model, that is, the horizontal direction. In this case, the angle of the dehydration screen is 0. The height of the four outriggers is the same, and there are installation holes for expansion wires on the four legs, which can be installed on the prefabricated concrete floor, in case the excitation force is too large at the moment of start and stop during use, causing the screen machine to move. bit.
4. If the customer has an inclination requirement for the angle of the dewatering screen, the manufacturer will also adjust the angle according to the customer's requirements to meet the production requirements.
Check items before installation of PU dewatering screen
1. Check whether the packaging of the dehydration screen is complete and whether the equipment is damp.
2. Check whether the vibrating motor of the dewatering screen is deformed or damaged during transportation, whether the parts are complete, and whether the fasteners are loose or falling off.
3. Check the nameplate on the vibrating motor of the dewatering screen to confirm whether the data meets the requirements.
4. Use a 500V megohmmeter to check that the insulation resistance of the stator winding to ground must not be less than 20 megohms. Otherwise dry the stator windings. During the drying process, the temperature should be uniform and should not exceed 120°C.

Installation steps of PU dewatering screen
1. Fasten the dewatering screen motor on the installation surface, the motor can be installed horizontally.
2. The motor lead wire adopts four-core rubber cable YZ-500V, and the lead wire cable is not allowed to have sharp bends when connected to the power supply, and it must be fixed reliably with the vibrating body.
3. The motor should be reliably grounded. There is a grounding device inside the motor, and there are marks on the lead end. It can also be grounded with solid bolts on the foot.
4. After confirming that the dewatering screen is installed firmly, its exciting force needs to be adjusted.
The above is the relevant introduction of Xinruituo's editor for the installation precautions of the PU dewatering screen. It can be seen from the introduction that when there is no fixed requirement for the installation angle of the dewatering screen, it is usually installed horizontally. If the customer has tilt requirements, adjust the installation angle according to customer requirements. Shandong XinRuiTuo Precision Industry Co., Ltd. produces high-quality dewatering screens. If you have other questions, welcome to inquire us.